ACPL Rejuvenation Project

Construction Photos and Updates

Construction Update: Week of April 7-11

Photo of meeting room renovation. Text in graphic notes: It’s been fairly noisy these past few weeks at ACPL. Behind the scenes, the construction crew has trenched the plumbing path for the Meeting Room kitchenette and new single-user bathroom in the lobby.
Photos of front entrance renovation. Text in graphic notes: At the front entrance, the majority of the concrete pad has been removed. The construction crew has also removed the old tile that was the old lobby floor. Plumbing for the new single-user bathroom has been installed. A portion of the exterior brick has been removed. This will be the new public entrance to the Meeting Room.

Construction Update: Week of March 31 - April 4

Photos of Activity Center construction. Text in graphic notes: ACPL kiddos were excited to have a close up look at some of the construction progress this week!
Photo of front entrance renovation. Text in graphic notes: The concrete floor has almost all been removed from the front entrance area. A new floor will be poured during the project. You can also see the start of removing the brick wall to construct the new public entrance to the ACPL meeting room.

Construction Update: Week of March 24-28

Photos of progress on Activity Center construction.
Photos of front entrance construction.

Construction Update: Week of March 17-21

Photos of the exterior of the Activity Center being built.
Photos of wall going up in meeting room. Text in graphic notes: ACPL’s old, moveable wall between the Meeting Room and staff offices was removed and replaced with a permanent wall. This will help with sound issues in the meeting room and provide a better working environment for staff.

Construction Update: Week of March 10-14

Text in graphic says ACPL Construction Corner. Meeting Room. So far... ACPL's Meeting Room has gone through the demolition phase. Goodbye old & stained carpet! What's next? The Meeting Room will be used for storage/staging while the crew works on other areas. Three photos depict the meeting room in its current state from various angles. There are lights hanging from the ceiling. There are ladders and pallets throughout. There are metal beams along the walls framing new walls. There is an uncarpeted floor that looks like it may be concrete with carpet glue.
Text in graphic says ACPL Construction Corner. Activity Center. So far... There has been a lot of activity on the front of the building for the future home of the Activity Center. What's next? More exterior work. Four photos depict a construction vehicle next to a large pile of dirt, the patio area on the north side of the building where the activity center is being built, a construction vehicle with its digging aparatus in a large hole, and an area with some walls being framed out.
Text within graphic says ACPL Construction Corner. Misc Extras. Text captioning photos says Above: A ramp and an alcove were added to the building to serve as a temporary entrance during construction. Right: Sadly, ACPL lost one of its favorite trees due to frost damage. We said a fond farewell to this great tree. Left: Wow, could there be more design decisions during construction. Four photos depict the new ramp and alcove during their construction, the new temporary entrance during its construction, the tree with white bark and black stripes that was on the northwest side of the building, and Caitlin and Rachel holding a sample book trying to make decisions.